Spuyten Duyvil Playground Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the spray shower at Spuyten Duyvil Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Adjusted Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • City Council
  • State

Location

Spuyten Duyvil Playground , Bronx
Douglas Avenue between West 235th Street, and West 236th Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/22/2018