Spuyten Duyvil Playground Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct the spray shower at Spuyten Duyvil Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,055,000
Funding Sources:
  • City Council
  • State

Location

Spuyten Duyvil Playground , Bronx
Douglas Avenue between West 235th Street, and West 236th Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2018