Silent Spring Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Silent Spring Playground in Kissena Corridor Park.
Project Timeline
Design
Start Date: January 2016
Projected Completion Date:
July 2016
Completion Date:
September 2016
Procurement
Start Date: September 2016
Projected Completion Date:
June 2017
Completion
Date:
October 2017
Construction
Start Date: December 2017
Projected Completion Date:
December 2018
Completion
Date:
December 2018
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
Location
Kissena Corridor Park
, Queens
Colden Street between Juniper Avenue and Geranium Avenue
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/15/2021