Rockaway Beach Shore Front Parkway Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the handball courts at Rockaway Beach.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: November 2016
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Rockaway Beach Boardwalk , Queens
Shore Front Parkway between Beach 102nd Street and Beach 105th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2018