Rockaway Beach Shore Front Parkway Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    77% complete

This project will reconstruct the handball courts at Rockaway Beach.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: November 2016
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: November 2018

Construction

Start Date: March 2019
Projected Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $3,723,000