NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Poe Cottage Landscape and Accessible Path Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct an accessible entrance to Poe Cottage and reconstruct surrounding landscape including planting, pavements and fencing.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: August 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $500,000
Funding Source: City Council

Location

Poe Park, Bronx
Poe Park, Grand Concourse between East Kingsbridge Road and East 192nd Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/04/2017