NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Millbrook Park Basketball and Handball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    23% complete

This project will reconstruct the basketball and handball courts and complete miscellaneous site work at Millbrook Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: March 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: April 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $975,000
Funding Sources:
  • Borough President
  • City Council

Location

Millbrook Playground, Bronx
Mill Brook Park at Bruckner Boulevard between Cypress and St. Ann's Avenues

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?