Co-Op City Field Irrigation System Installation

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will install an irrigation system at Co-op City Field.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Adjusted Completion Date: February 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Co-op City Field , Bronx
Co-op City Boulevard, Bellamy Loop, Hutchinson River

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/22/2020