Hunts Point Riverside Park Dock Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the dock in Hunts Point Riverside Park, including the piles, dock, gangway and pier.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: August 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Hunts Point Riverside Park , Bronx
Edgewater Road and Lafayette Avenue, along the Bronx River

 

Project Staff

Contact NYC Parks about this project

Last updated: 09/25/2020