Hunts Point Riverside Park Dock Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the dock in Hunts Point Riverside Park, including the piles, dock, gangway and pier.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: August 2020
Adjusted Completion Date: October 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Hunts Point Riverside Park , Bronx
Edgewater Road and Lafayette Avenue, along the Bronx River

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 08/08/2022

Was this information helpful?