Riverside Park 109th Street Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the existing skate park with new skate elements, fencing, benches, picnic tables, and landscaping at West 109th Street in Riverside Park.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: March 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: December 2018
Adjusted Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Riverside Park , Manhattan
Between Henry Hudson Parkway and Riverside Drive at West 109th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/22/2019