Citywide DCAS Accelerated Conservation & Efficiency Program (CNYG-2415MA1)

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will upgrade lighting fixtures to improve energy efficiency at various locations citywide.

Project Update: The contract was submitted to the Comptroller’s office for registration.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: November 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Adjusted Completion Date: September 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral