Citywide DCAS Accelerated Conservation & Efficiency Program (CNYG-2415MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will upgrade lighting fixtures to improve energy efficiency at various locations citywide.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: November 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $2,273,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/16/2017