Citywide DCAS Accelerated Conservation & Efficiency Program (CNYG-2415MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will upgrade lighting fixtures to improve energy efficiency at various locations citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: November 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: November 2020