Noble Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort station at Noble Playground.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019
Completion Date: March 2021

Construction

Start Date: June 2021
Projected Completion Date: September 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,400,000
Funding Sources:
  • Borough President
  • City Council

Location

Noble Playground , Bronx
East 177th Street between Noble Avenue and Bronx River Parkway

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 07/01/2022