Noble Playground Comfort Station Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the comfort station at Noble Playground.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
June 2019
Adjusted Completion
Date:
March 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Noble Playground
, Bronx
East 177th Street between Noble Avenue and Bronx River Parkway
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 12/06/2019