Colonel David Marcus Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Colonel David Marcus Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $567,000
Funding Source: City Council

Location

Colonel David Marcus Playground , Brooklyn
Avenue P between East 4th Street and East 5th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/19/2018