Colonel David Marcus Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Colonel David Marcus Playground.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Adjusted Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Colonel David Marcus Playground , Brooklyn
1662 East 5 Street Located North of Ave. P between E 4th St. and E 5th St.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/15/2018