Colonel David Marcus Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Colonel David Marcus Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Source: City Council

Location

Colonel David Marcus Playground, Brooklyn
1662 East 5 Street Located North of Ave. P between E 4th St. and E 5th St.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/16/2018