NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Fulton Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    10% complete

This project will reconstruct the comfort station at Fulton Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: September 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: July 2017

Construction

Start Date: November 2017
Projected Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $1,342,000
Funding Sources:
  • Mayoral
  • City Council

Location

Fulton Park, Brooklyn
Stuyvesant Avenue between Chauncey and Fulton Streets

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/16/2018