NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Wolfe's Pond Park Playground Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    48% complete

This project will reconstruct the Sandy-damaged playground and adjacent pathways, including installation of new full depth asphalt pavement for existing paths, the removal and reinstallation of all existing safety surfacing surrounding the play equipment as well as repairs to existing chain link fencing, benches and curbs.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: June 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: January 2016
Completion Date: April 2017

Construction

Start Date: May 2017
Projected Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $959,000
Funding Sources:
  • Mayoral
  • Federal

Location

Wolfe's Pond Park, Staten Island
The playground is located along the shoreline of Wolfe''s Pond Park at Cornelia Avenue and the Raritan Bay.

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?