Wolfe's Pond Park Playground Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Sandy-damaged playground and adjacent pathways at Wolfe's Pond Park, including new asphalt pavement, safety surfacing, fencing, benches, and curbs.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: June 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: January 2016
Completion Date: April 2017

Construction

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $732,000
Funding Sources:
  • Mayoral
  • Federal

Location

Wolfe's Pond Park , Staten Island
Cornelia Avenue, Chester Avenue, Raritan Bay

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project