Bayside Marina Electrical Systems Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This contract will replace electrical equipment, conduits and cable damaged by Hurricane Sandy at Bayside Marina.
Project Timeline
Design
Start Date: July 2014
Projected Completion Date:
January 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
July 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion
Date:
May 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Cross Island Parkway
, Queens
Cross Island Parkway and 28th Avenue
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project