Bayside Marina Electrical Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    50% complete

This contract will replace electrical equipment, conduits and cable damaged by Hurricane Sandy at Bayside Marina.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: January 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $411,000
Funding Sources:
  • Mayoral
  • Federal

Location

Cross Island Parkway , Queens
Bayside Marina, 28-05 Cross Island Parkway, Bayside

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/23/2018

Was this information helpful?