Kolbert Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball courts and expand the play area to include new basketball courts, new synthetic turf field & walking track, new play equipment, and new adult fitness equipment.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: November 2015
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: December 2016
Completion Date: December 2016

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,861,000
Funding Sources:
  • Borough President
  • City Council

Location

Kolbert Playground , Brooklyn
Avenue L, East 17th and East 18th Streets

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/20/2018