NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

McGolrick Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct the playground including, play equipment, spray shower, pavement, fencing, benches, and plantings.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: August 2015
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: March 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $2,639,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Msgr. McGolrick Park, Brooklyn
Park is bounded by Nassau Avenue, Monitor Street, Russell Street and Driggs Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?