Stroud Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct the playground, multi-use area, landscaping, play equipment, safety surface, spray shower, seating areas, basketball court and handball court at Stroud Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $5,028,000
Funding Sources:
  • Mayoral
  • City Council

Location

Stroud Playground, Brooklyn
Stroud Playground West of Classon Avenue Between Park Place and Sterling Place.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/18/2017