NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Buono Beach and Alice Austen Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the landscape elements at Alice Austen House including picket fences and paths due to damage sustained during Hurricane Sandy. The project will also include the installation of security lighting.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: March 2015
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Federal

Location

Alice Austen Park, Staten Island
Edgewater Street and Hylan Boulevard

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 02/16/2018

Was this information helpful?