Nelson Avenue Waterfront Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    62% complete

This project will repair the Hurricane Sandy-damaged playground and landscape at Nelson Avenue Waterfront Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: March 2015
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Adjusted Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $966,000
Funding Sources:
  • Mayoral
  • Federal

Location

Seaside Wildlife Nature Park , Staten Island
Cleveland and Nelson Avenues, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 12/15/2018