Nelson Avenue Waterfront Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    17% complete

This project will repair the Hurricane Sandy-damaged playground and landscape at Nelson Avenue Waterfront Park.

Project Update: This project is in active construction.

Project Timeline


Start Date: April 2014
Projected Completion Date: March 2015
Completion Date: January 2015


Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: June 2017


Start Date: October 2017
Projected Completion Date: October 2018

Understand how we build parks.


Total Funding: $966,000
Funding Sources:
  • Mayoral
  • Federal


Seaside Wildlife Nature Park , Staten Island
Cleveland and Nelson Avenues, Staten Island


Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 03/16/2018