Nelson Avenue Waterfront Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Hurricane Sandy-damaged playground and landscape at Nelson Avenue Waterfront Park.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: March 2015
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,869,000
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Seaside Wildlife Nature Park , Staten Island
Cleveland Avenue and Nelson Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project