Manhattan General Site Work (MG-315MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct pavements, basketball courts, fencing and general site work at various locations in Manhattan.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: January 2015
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: August 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $809,000
Funding Source: Mayoral

Locations

  • Highbridge Park, Manhattan
    W 155 St & Dyckman St, Edgecombe Av & Amsterdam Av
  • Riverside Park, Manhattan
    Riverside Dr. to Hudson River, W. 72 St.to St Clair Pl.
  • St. Nicholas Park, Manhattan
    St Nicholas Av To St Nicholas Terr, W 128 St To W 141 St
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/18/2017