Tribute Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct Tribute Park due to damage from Hurricane Sandy.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $2,288,000
Funding Sources:
  • Mayoral
  • Federal

Location

Tribute Park , Queens
Beach Channel Drive Between Beach 116th and Beach 117th Streets.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2018