Forest Park Greenhouse Palm House Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the Palm House at the Forest Park Greenhouse.
Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.
Project Timeline
Design
Start Date: December 2015
Projected Completion Date:
March 2018
Completion Date:
November 2021
Procurement
Start Date: July 2019
Projected Completion Date:
April 2020
Adjusted Completion
Date:
August 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
- Federal
Location
Forest Park
, Queens
Woodhaven Boulevard, Myrtle Avenue, Forest Park Drive, 88th Lane
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 05/20/2022