Junction and Corona Golf Playground Play Equipment Installation (QG-615M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install special needs play equipment for Fort Totten and Crocheron Park and a safety surface for Corona Golf and Junction Playground.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: December 2014
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: March 2016

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,983,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/07/2020