Nautilus, Walter Ward, and Cambria Playgrounds Basketball and Handball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct basketball and handball courts at Nautilus Playground and Cambria Playground, and the basketball courts at Walter Ward Playground.
Project Timeline
Design
Start Date: July 2014
Projected Completion Date:
March 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
February 2016
Completion
Date:
April 2016
Construction
Start Date: June 2016
Projected Completion Date:
December 2017
Completion
Date:
March 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Cambria Playground, Queens
121 Avenue & 220 Street -
Roy Wilkins Recreation Center, Queens
Baisley & Merrick Boulevards, 115 Avenue -
Walter Ward Playground, Queens
89 St and 160 Av
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022