Twenty-Four Sycamores Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Twenty-Four Sycamores Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: March 2016
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Twenty-Four Sycamores Park , Manhattan
FDR Drive, East 60th Street, East 61st Street, York Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project