Grandview Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, courts, and multi-use fields in Grandview Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: January 2017
Completion Date: January 2017

Construction

Start Date: January 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $4,475,000
Funding Sources:
  • Mayoral
  • City Council

Location

The Big Park , Staten Island
Grandview Avenue & Continental Place.

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 08/20/2018