Citywide Electrical System Reconstruction for Comfort Stations & Parks Facilities (CNYG-615M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct comfort stations at facilities citywide.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: July 2014
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: July 2016

Construction

Start Date: September 2017
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $865,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/21/2017