Citywide Electrical System Reconstruction for Comfort Stations & Parks Facilities (CNYG-615M)

  • Design
    100 % complete 
  • Procurement
    100% complete  
  • Construction
     

This project will construct comfort stations at facilities citywide.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: July 2014
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: July 2016

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayor

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/25/2017