Citywide Pool Plumbing Systems Reconstruction (CNYG-915M)

  • Design
    100 % complete 
  • Procurement
    100% complete  
  • Construction
    3% complete  

This project will reconstruct deteriorated plumbing systems at various pool facilities citywide.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: July 2014
Completion Date: December 2014

Procurement

Start Date: December 2014
Projected Completion Date: September 2015
Completion Date: June 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Mayor

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/25/2017