Citywide Pool Electrical Systems Reconstruction (CNYG-815MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    21% complete

This project will reconstruct deteriorated electrical systems at various pool facilities citywide.

Project Update: This project is in active construction.

Project Timeline


Start Date: June 2014
Projected Completion Date: July 2014
Completion Date: October 2015


Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: September 2016


Start Date: October 2016
Projected Completion Date: October 2019

Understand how we build parks.


Total Funding: $1,500,000
Funding Source: Mayoral



Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/21/2018