NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Manhattan Roofing Systems Reconstruction (MG-215M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    28% complete

This project will reconstruct the roofing systems at various facilities in Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: November 2016

Construction

Start Date: March 2017
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,750,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 02/16/2018

Was this information helpful?