Citywide Pool Systems Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    0% complete 

This project will reconstruct deteriorated structural systems at various pool facilities citywide.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date:July 2014
Completion Date: December 2014

Procurement

Start Date: December 2014
Projected Completion Date:September 2015
Completion Date: June 2016

Construction

Start Date: October 2016
Projected Completion Date:September 2019

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Source:Mayor

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 02/21/2017