Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-415M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roofing systems at various facilities in Brooklyn and Staten Island.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: November 2015

Construction

Start Date: March 2016
Projected Completion Date: March 2018
Completion Date: July 2017

Understand how we build parks.

Funding

Total Funding: $1,900,000
Funding Source: Mayoral

Locations

  • Betsy Head Park , Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • Canarsie Park , Brooklyn
    Seaview Avenue between Paerdegat Basin and East 93 Street, East 102 Street and Fresh Creek Basin
  • Clove Lakes Park , Staten Island
    Clove Road & Forest Avenue
  • Heckscher Playground , Brooklyn
    Linden Street between Central Avenue and Wilson Avenue
  • Jackie Robinson Playground , Brooklyn
    Sullivan Place & Franklin Avenue, Montgomery Street
  • Sunset Park , Brooklyn
    41 Street, 44 Street, between 5 Avenue and 7 Avenue
 