Bronx and Queens Roofing Systems Reconstruction (CNYG-315MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    51% complete

This multisite contract will reconstruct roofing systems at various sites in the Bronx and Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Mayoral

Locations

  • Bronx Park, Bronx
    Burke Ave., E. 180 St. bet. Dr. Kazamiroff Blvd., Southern Blvd. and Bronx Park E., Unionport Rd.
  • Corona Golf Playground, Queens
    109 Street between 46-47 Avenues
  • Crotona Park, Bronx
    Crotona Park North to South, Fulton Av to Southern Blvd & Crotona Park East
  • Forest Park, Queens
    (Southeast) West Main Drive to Eastern Side of Gold Course
  • Forest Park, Queens
    Myrtle Avenue, Union Turnpike, Park Lane South
  • Fort Totten Park, Queens
    Cross Island Pkwy. bet. Totten Ave. and 15 Rd.
  • Mott Playground, Bronx
    Morris Av bet Mc Clellan St & E 166 St
  • Poppenhusen Playground, Queens
    20 Avenue between 123 Street and 124 Street
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/18/2017