Bronx and Queens Roofing Systems Reconstruction (CNYG-315MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofing systems at various sites in the Bronx and Queens.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2019
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,582,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/19/2020