Flushing Meadows Corona Park Meadow Lake Northwest Area Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the pedestrian and vehicle pathways in Flushing Meadow Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: September 2020
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021
Adjusted Completion Date: July 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Flushing Meadows Corona Park , Queens
Northwest side of Meadow Lake, east of Grand Central Parkway between Long Island Expressway and 64th Road.

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/05/2022

Was this information helpful?