Cunningham Park Picnic Area Reconstruction and Performance Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will reconstruct the picnic area and the adjacent pathways, and construct a performance area in Cunningham Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date: March 2016
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: January 2017
Completion Date: March 2017

Construction

Start Date: June 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $2,236,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Cunningham Park, Queens
Grand Central Parkway between 193rd Street, Francis Lewis Boulevard, Hollis Hills Terrace and 210th Street.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017