Brookville Park Picnic Area Reconstruction and Tennis Courts Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the picnic area and construct a tennis court and lighting at Brookville Park.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: May 2016
Completion Date: April 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $2,739,000
Funding Sources:
  • Mayoral
  • City Council

Location

Brookville Park , Queens
Brookville Boulevard, 232nd Street, 144th Avenue and 145th Avenue.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project