NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Elmhurst Park Vietnam Veterans Memorial Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a Queens Vietnam Veterans memorial in Elmhurst Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Elmhurst Park , Queens
located at Grand Avenue between 57th Avenue and 79th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 04/26/2018

Was this information helpful?