Sandpiper Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Sandpiper Playground.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: May 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Rockaway Beach Boardwalk , Queens
On Shore Front Parkway between Beach 105th Street and Beach 108th Street at Rockaway Beach, Borough of Queens.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/23/2018