Big Bush Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, handball courts, sitting area, fencing and pavements in Big Bush Park.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: December 2015
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: February 2017

Construction

Start Date: May 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,717,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Big Bush Playground , Queens
Laurel Hill Boulevard between 61st Street and 64th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project