Joe Devoy Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Joe Devoy Playground in Forest Park.
Project Timeline
Design
Start Date: September 2014
Projected Completion Date:
August 2015
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
April 2016
Construction
Start Date: June 2016
Projected Completion Date:
June 2017
Completion
Date:
January 2017
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Forest Park
, Queens
Union Turnpike and 71st Avenue
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/17/2022