Laurelton Playground and Bayswater Park Skate Elements and Seating Areas Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will provide skate park elements and related site amenities.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: July 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: October 2017
Completion Date: October 2017

Construction

Start Date: October 2017
Projected Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $2,837,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017