College Point Fields Sports Complex Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    72% complete

This project will construct a football field at College Point Fields.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2016
Projected Completion Date: January 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: October 2022

Understand how we build parks.

Funding

Total Funding: $7,483,000
Funding Sources:
  • City Council
  • Mayoral

Location

College Point Fields , Queens
Linden Place, 23rd Avenue, Ulmer Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 08/10/2022