College Point Fields Sports Complex Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a football field at College Point Fields.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2016
Projected Completion Date: January 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

College Point Fields , Queens
Linden Place, 23rd Avenue, Ulmer Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/19/2019