Bowne Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and basketball court in Bowne Park.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: August 2015
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: August 2017

Understand how we build parks.

Funding

Total Funding: $1,438,000
Funding Sources:
  • Borough President
  • City Council

Location

Bowne Park , Queens
155th Street, 159th Street, 29th Avenue, 32nd Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/28/2020