Clement Clarke Moore Homestead Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    63% complete

This project will reconstruct the playground, spray shower, and pavements at Clement Clarke Moore Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: March 2020
Adjusted Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $5,108,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Moore Homestead Playground , Queens
Broadway, 45th Avenue, 82nd Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 03/31/2020