Roy Wilkins Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Roy Wilkins Park Recreation Center.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: June 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Roy Wilkins Recreation Center , Queens
Merrick Blvd. bet. 115 Ave., 116 Ave., and Baisley Blvd.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/15/2018