Roy Wilkins Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Roy Wilkins Park Recreation Center.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: June 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Adjusted Completion Date: December 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Roy Wilkins Recreation Center , Queens
Merrick Blvd. bet. 115 Ave., 116 Ave., and Baisley Blvd.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/16/2019