Canarsie West Trail Connector Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi-use greenway path connecting the on-street path along Paerdegat Avenue North to the Shore Parkway Greenway along the southwestern edge of Canarsie Park.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: October 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: April 2017

Construction

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $899,000
Funding Source: Federal

Location

Canarsie Park , Brooklyn
Paerdegat Avenue North & Seaview Avenue to Shore Parkway

 

Project Staff