Morningside Park 123rd Street Playground Reconstruction Phase II

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will include play equipment, seating, planting, lighting, pavements and fencing, and drainage and water supply systems.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: November 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: January 2018
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $2,540,000
Funding Source: City Council

Location

Morningside Park, Manhattan
Located at West 123rd Street and Morningside Avenue in Morningside Park

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/16/2018