Theodore Roosevelt Park Dog Run Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Bull Moose Dog Run in Theodore Roosevelt Park.
Project Timeline
Design
Start Date: July 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion
Date:
July 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Theodore Roosevelt Park
, Manhattan
West 81st Street and Central Park West
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/26/2021