Theodore Roosevelt Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Bull Moose Dog Run in Theodore Roosevelt Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Borough President
  • City Council

Location

Theodore Roosevelt Park , Manhattan
West 81st Street and Central Park West

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project