Sara D. Roosevelt Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct a comfort station in Building A in Sara D Roosevelt Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: July 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Sources:
  • Borough President
  • City Council

Location

Sara D. Roosevelt Park, Manhattan
Located between Chrystie Street, Forsyth Street, Stanton Street, and East Houston Street in the Borough of Manhattan.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/14/2017