Seaside Wildlife Nature Park Comfort Station Construction
-
100% complete
-
5% complete
-
0% complete
This project will construct a comfort station in Seaside Wildlife Nature Park
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: December 2018
Projected Completion Date:
December 2019
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Seaside Wildlife Nature Park
, Staten Island
Nelson Avenue at Tennyson Drive
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 04/09/2021