Seaside Wildlife Nature Park Comfort Station Construction
-
100% complete
-
60% complete
-
0% complete
This project will construct a comfort station in Seaside Wildlife Nature Park
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
Project Timeline
Design
Start Date: December 2018
Projected Completion Date:
December 2019
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Adjusted Completion
Date:
June 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Seaside Wildlife Nature Park
, Staten Island
Nelson Avenue at Tennyson Drive
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 07/01/2022